- Surface area
- 2,750 m²
- Year
- 2025
Offshore wind secondary steel
Boat landings, platforms and ladders for offshore wind foundations, protected with thermal-sprayed aluminium.
- Heavy industry
- Blasting
- Metallizing
- Industrial coating
- Temse

An 80-tonne boom metallized and coated for a life in salt spray and abrasive bulk dust.
A dry bulk terminal replaced the boom of one of its ship-loaders. The new section, 38 metres and 80 tonnes, would spend its life above the water in salt spray, with coal and ore dust scouring every surface. The old boom had needed paint repairs every few years, and each one meant downtime at the quay.
Temse sits on the Scheldt, so a piece this size can come straight off a pontoon into our hall. We blasted the boom to Sa 3 in one run and metallized it with zinc-aluminium, which holds up better than pure zinc in a marine atmosphere. A sealer closed the porous metal layer, followed by a polyurethane topcoat in the terminal’s safety yellow. Inside the box section, we checked every drain opening so no water can collect.
The boom left on schedule after three weeks, ready for installation. With a duplex system, the terminal expects to go well past the old repaint interval, which means fewer stops for the loader.
Gallery


Related projects

Boat landings, platforms and ladders for offshore wind foundations, protected with thermal-sprayed aluminium.

1.2 km of crane runway for a steel service centre, blasted and coated in four weeks.

Our team handles the work. You get the results. Let's talk.