Refinery fire protection
Epoxy intumescent on column skirts and support steel, rated for 90 minutes of hydrocarbon fire.
- Petrochemistry
- Blasting
- Fire coating
- Lokeren

Modular pipe racks for a chemical plant expansion, coated and fireproofed in four batches.
An EPC contractor was building a new production unit on a chemical site, with the pipe racks prefabricated as modules to shorten the site schedule. All steel needed a C5 anticorrosion system. The lower tiers, which carry the process lines, also needed protection against a hydrocarbon fire.
We split the order into four batches that matched the module assembly sequence. All steel was blasted and coated in Lokeren, and the members for the lower two tiers then got an epoxy intumescent layer on top. Bracing connections and bolt holes were masked so the modules could be assembled without grinding off coating. One coordinator updated the contractor’s planner every day on what had left the hall.
The modules were assembled in the contractor’s yard and shipped to site with no coating repairs beyond the bolted joints. Moving all coating to the shop took the painting crew off the site schedule entirely.
Gallery


Related projects

Epoxy intumescent on column skirts and support steel, rated for 90 minutes of hydrocarbon fire.

New shell courses and roof plates for two 20,000 m³ tanks, lined inside and coated outside before erection.

Our team handles the work. You get the results. Let's talk.